- Cold Hydrostatic Testing successfully completed at Unit 4 of the Barakah Nuclear Energy Plant
 
 
19 May 2020, Abu Dhabi, UAE:  The Emirates Nuclear Energy Corporation (ENEC) has successfully completed Cold Hydrostatic Testing (CHT) at Unit 4 of the Barakah Nuclear Energy Plant, the Arab world’s first nuclear energy plant being built in the Al Dhafra region of Abu Dhabi, UAE. The testing incorporated the lessons learned from the previous three units and is a crucial step towards the completion of Unit 4, the final unit of the Barakah plant.
 
As a part of CHT, the pressure inside Unit 4’s systems was increased to 25% above what will be the normal operating pressure, demonstrating the quality and robust nature of the Unit’s construction. Prior to the commencement of CHT, Unit 4’s Nuclear Steam Supply Systems were flushed with demineralized water, and the Reactor Pressure Vessel Head and Reactor Coolant Pump Seals were installed. During the Cold Hydrostatic Testing, the welds, joints, pipes and components of the reactor coolant system and associated high-pressure systems were verified.
 
H.E. Mohamed Al Hammadi, Chief Executive Officer of ENEC said: “I am proud of the continued progress being made at Barakah despite the circumstances we have all faced in relation to COVID-19. The UAE leadership’s decisive and proactive response to the pandemic supported us in taking timely, safety-led actions to protect the health and safety of our workforce and our plant. These actions, alongside the efforts of our talented and dedicated workforce, have enabled the successful completion of CHT at Unit 4, which was completed in adherence to the highest standards of safety, quality, and security.”
 
“With this accomplishment, we move another step closer to achieving our goal of supplying up to a quarter of our nation’s electricity needs and powering its future growth with safe, reliable, and emissions-free electricity,” concluded Al Hammadi. 
 
By the end of 2019, ENEC and Korea Electric Power Corporation (KEPCO) had successfully completed all major construction work including major concrete pouring, installation of the Turbine Generator, and the internal components of the Reactor Pressure Vessel (RPV) of Unit 4, which paved the way for the commencement of testing and commissioning.
 
The testing at Unit 4 represents a significant achievement in the development of the UAE Peaceful Nuclear Energy Program, following the successful completion of fuel assembly loading into Unit 1 in March 2020, confirming that the UAE has officially become a peaceful nuclear energy operating nation. Preparations are now in the final stages for the safe start-up of Unit 1 in the coming months.  
 
ENEC is currently in the final stages of construction of units 2, 3 and 4 of the Barakah Nuclear Energy Plant. The overall construction of the four units is more than 94% complete. Unit 4 is more than 84%, Unit 3 is more than 92% and Unit 2 is more than 95%. The four units at Barakah will generate up to 25% of the UAE’s electricity demand by producing 5,600 MW of clean baseload electricity, and preventing the release of 21 million tons of carbon emissions each year – the equivalent of removing 3.2 million cars off the roads annually.

 

Share


Previous in Business and Economy

Next in Business and Economy


Home >> Business and Economy Section

Latest Press Release

“Dubai Customs” celebrates the graduation of the first cohort of participants in the security refres ...

G-SHOCK's Summer Style Statement: Metal-Cased Watches That Define the Season

Hatta Hosts Summer Sports Festival to Attract Over 6,000 Participants as Part of 'Our Summer is Spor ...

flydubai breaks ground on new Aircraft Maintenance Centre at Dubai South

The most common mistakes in the care and use of your car's tyres

UAE Team Emirates-XRG and Tadej Pogačar aim for fourth Tour de France title

Dubai Airports hosts guided travel simulation experience for children with autism spectrum disorder ...

Vacheron constantin presents les cabinotiers Temporis duo grand complication openface

Emirates arrives in Shenzhen

Sorbonne University Abu Dhabi and Électricité de France Forge Sustainability-Focused Partnershi ...

Khalifa Fund for Enterprise Development's Abu Dhabi SME Champions Program facilitates 650+ deals wor ...

Gargash Group Accelerates Sustainability Agenda with New Sustainability Linked Facility from Mashreq

Hamdan Smart University Launches College of Sustainability and Green Economy

Mohammed Bin Rashid Innovation Fund Launches a New Chapter to Strengthen Government Innovation

RTA Completes Traffic Upgrades to Improve Connectivity Between Sheikh Zayed Road and Al Khail Road v ...

Dubai Municipality Announces Registration Opening for the Second Edition of the Food Systems Excelle ...

Emirates Aviation University marks 35 years of supporting the local and global aviation ecosystem

Emirates layers on retrofitted aircraft with latest product, including Premium Economy to more citie ...

Music, Maps, and Stories at the Mohammed Bin Rashid Library in July

New SHEGLAM Daydreamer Mini Palette Turns Pocket-Sized into Power Pigment